An earth pressure balanced shield TBM with the diameter of 4.4 m was designed and manufactured for a subsea discharge tunnel excavation. Its cutterhead was designed to be optimized for the strongest rock mass condition in the tunnel alignment, and then the applicability of the refurbished shield TBM was validated for its maximum capacity. Especially, the maximum cutter penetration depth for the strongest rock mass condition should be kept to be below 7 mm/rev in order to satisfy the allowable capacities of the shield TBM. From the analysis of TBM advance data, approximately 95% of field data showed the cutter penetration depth below 7 mm/rev. In addition, it was certified that the acting forces of every disc cutter, TBM thrust and torque during TBM driving were within the allowable capacities of the shield TBM and its disc cutters. When real acting forces of the disc cutters in the field were compared with those predicted by the CSM model, they showed the close relationships with each other even though the predictions by the CSM model were approximately 22∼25% higher than field data.

keywords
TBM, 커터헤드, 디스크커터, 커터 작용력, 굴진성능, TBM, Cutterhead, Disc cutter, Cutter acting force, Excavation performance

Reference

1.

1. Bae, G.-J., Chang, S.-H. (2006), “Improvement and evaluation of TBM performance by considering construction risk”, Proceedings of the 7th Symposium on Mechanized Tunnelling Technology, pp. 11-45(in Korean).

2.

2. Cho, J.W., Jeon, S.W., Jeong, H.Y., Chang, S.H. (2013), “Evaluation of cutting efficiency during TBM disc cutter excavation within a korean granitic rock using linear-cutting-machine testing and photogrammetric measurement”, Tunnelling and Underground Space Technology, Vol. 35, pp. 37-54.

3.

3. Cho, J.W., Jeon, S.W., Yu, S.H., Chang, S.H. (2010), “Optimum spacing of TBM disc cutters:A numerical simulation using the three-dimensional dynamic fracturing method”, Tunnelling and Underground Space Technology, Vol. 25, pp. 230-244.

4.

4. Chang, S.-H., Choi, S.-W., Park, Y.-T., Lee, G.-P., Bae, G.-J. (2013), “Experimental evaluation of the effects of cutting ring shape on cutter acting forces in a hard rock”, Journal of Korean Tunnelling and Underground Space Association, Vol. 15, No. 3, pp. 225-235 (in Korean).

5.

5. Chang, S.-H., Choi, S.-W., Park, Y.-T., Lee, G.-P., Bae, G.-J. (2012), “Characterization of the deformation of a disc cutter in linear rock cutting test”, Journal of Korean Tunnelling and Underground Space Association, Vol. 14, No. 3, pp. 197-213(in Korean).

6.

6. Chang, S.-H., Choi, S.-W., Lee, G.-P., Bae, G.-J. (2011), “Rock TBM design model derived from the multi-variate regression analysis of TBM driving data”, Journal of Korean Tunnelling and Underground Space Association, Vol. 13, No. 6, pp. 531-555 (in Korean).

7.

7. Chang, S.-H., Choi, S.-W., Lee, G.-P., Bae, G.-J. (2011), “Statistical analysis of NTNU test results to predict rock TBM performance”, Journal of Korean Tunnelling and Underground Space Association, Vol. 13, No. 3, pp. 243-260 (in Korean).

8.

8. Chang, S.-H., Choi, S.-W., Bae, G.-J., Jeon, S. (2007), “A parametric study of rock properties and mechanical cutting conditions for deriving an optimum design model of a TBM cutterhead equipped with disc cutters”, Journal of the Korean Society of Civil Engineers, Vol. 27, No. 1C, pp. 87-98 (in Korean).

9.

9. Choi, S.-W., Chang, S.-H., Park, Y.-T., Lee, G.-P., Bae, G.-J. (2013), “A experimental study on the loads and temperature acting on the shaft of a disc cutter during linear rock cutting test”, Journal of Korean Tunnelling and Underground Space Association, Vol. 15, No. 3, pp. 237-251(in Korean).

10.

10. Jeong, H.Y., Jeon, S.W., Cho, J.W. (2013), “A numerical study on rock cutting by a TBM disc cutter using SPH code”, Journal of Korean Tunnelling and Underground Space Association, Vol. 15, No. 3, pp. 345-356 (in Korean).

11.

11. Kim, S.H., Park, I.J., Chang, S.H. (2013), “Evaluation of disc cutter penetration depth of shield TBM in practice”, Journal of Korean Tunnelling and Underground Space Association, Vol. 15, No. 3, pp. 321-331 (in Korean).

12.

12. Lee, S., Jung, H., Jeon, S. (2012), “Determination of rock abrasiveness using cerchar abrasiveness test”, Tunnel & Underground Space, Vol. 22, No. 4, pp. 284-295 (in Korean).

13.

13. Nishimatsu, Y., Okuno, N., Hirasawa, Y.(1975), “The rock cutting with roller cutters”, J. of MMIJ, Vol. 91, pp. 653-658.

14.

14. Rostami, J. (2013), “Study of pressure distribution within the crushed zone in the contact area between rock and disc cutters”, International Journal of Rock Mechanics & Mining Sciences, Vol. 57, pp. 172-186.

15.

15. Rostami, J., Ozdemir, L., Nisen, B. (1996), “Comparison between CSM and NTH hard rock TBM performance prediction models”, Proc. of ISDT 1996, Las Vegas NV, pp. 1-11.

16.

16. Rostami, J. Ozdemir, L. (1993), “A new model for performance prediction of hard rock TBMs”, Proc. of Rapid Excavation and Tunneling Conference (RETC), Boston, USA, pp. 793-809.

17.

17. Snowdon, R.A., Ryley, M.D., Temporal, J. (1982), “A study of disc cutting in selected british rocks”, Int. J. Rock Mech. Min. Sci. & Geomech. Abstr., Vol. 19, pp. 107-121.

18.

18. TUNCONSTRUCT (2008), Going Underground, Graz University of Technology, Austria.

19.

19. Yun, D.-S., Jee, W., Cho, S.-H. (2013), “Case study on the home-made korean shield TBM cutting ability through subsea tunnel project”, Proceedings of KTA 2013 Fall Symposium, pp. 85-88 (in Korean).

(사)한국터널지하공간학회