Most tunnel damage such as cracks or leakage which exist in tunnel liner commonly, is caused by the cavities that exist behind the tunnel liner, through the tunnel safety inspections. These cavities were analysed to check if they affect the stability of tunnels. This study is on the development of the controlled low-strength and flowable filling material which an be applied to the cavity behind the tunnel lining. The backfilling material studied here is crushed sand and stone-dust which is in cake-state and is a by-product obtained in the producing process of aggregate. Varying the compound mixing ratio, laboratory tests of compression test and chemical analyses were carried out. In addition, the material was applied to an old tunnel for the performance assessment.