Risk management applicable to shield TBM tunnel: Ⅱ. Risk analysis methodology

(사)한국터널지하공간학회 / (사)한국터널지하공간학회, (P)2233-8292; (E)2287-4747
2012, v.14 no.6, pp.683-697





Abstract

In this paper, a risk analysis methodology applicable to shield TBM tunnels was studied. Fault Tree Analysis (FTA) was utilized to identify all risk items and to calculate the probability of failure of each item and Analytic Hierarchy Process (AHP) was used to obtain the impact of each risk item. Finally, a risk level of each risk item can be assessed. Developed methodology is applied to a Seoul subway site in which EPB shield tunnel method was utilized and it was found that risk analysis results matched reasonably well with field data.

keywords
쉴드 TBM 터널, 리스크 분석, 리스크 요인, fault tree analysis, analytic hierarchy process, Shield TBM tunnelling, risk analysis, risk factor, fault tree analysis, analytic hierarchy process

Reference

1.

Ku, B.H., Cha, J.M., Kim, H.C. (2008), “Reliability analysis of distribution systems by using FTA”, The Korean Institute of Electrical Engineers power engineering autumnal conference, pp. 247-249.

2.

Kim, K.J., Jang, M.S. (2006), “The method of results of decision reflections between PI project valuation groups using AHP”, Jounal of Korean Society of Road Engineers, Vol. 8., No. 4, pp. 145-157.

3.

Lee, H.C., Kim, S.K., Kim, O.K. (2007), “Development of decision making model for selecting the soft foundation improvement method using AHP technique”, Journal of Korean Society of Civil Engineers, Vol. 27., No. 4, pp. 499-506.

4.

Korean Tunnelling Association (2008), Series of Tunnel Engineering 3 - Tunnel Mechanized Construction Design, CIR, Seoul.

5.

Hong, E.S., Kong, J.S., Shin, H.S., Lee, I.M., (2007), “A Case Study for Probabilistic Risk Evaluation based on Event Tree Analysis Technique for the Design of Shield TBM”, Journal of Korean Society of Civil Engineers, Vol. 27., No. 2, pp. 139-147.