Designing TBMs for subsea tunnels

(사)한국터널지하공간학회 / (사)한국터널지하공간학회, (P)2233-8292; (E)2287-4747
2015, v.17 no.6, pp.587-596
Ruben Duhme (Herrenknecht Tunneling Equipment Co. China)
Thorsten Tatzki (Herrenknecht Asia Headquarters Pte. Ltd)
  • 다운로드 수
  • 조회수

Abstract

Recent years have shown great advances in the feasibility of long subsea tunnels. Projects such as the Channel Tunnel, the Stoerebelt Tunnel or the Bosporus Crossing have pushed the boundaries of TBM tunneling technology and fueled the work on feasibility studies for even more challenging projects such as crossing the Qiongzhou or Gibraltar Straits. There are numerous geotechnical challenges such as wide variations of ground conditions, high operation pressures or long tunnel distances and finally geological uncertainties which must be solved in order to attempt such projects. Several operational challenges such as large muck quantities interventions under difficult conditions and long transport distances also have to be tackled. TBM manufacturer and construction industry have developed a number of approaches to these challenges which point into the right technical direction and have been proven successfully in recent experiences. Their further development will allow attempting several megaprojects which are currently under discussion.

keywords
TBM, High pressures, Long distance, Subsea, Large diameter

참고문헌

1.

1. Anagnostou, G. (2010), Some rock mechanics aspects of subaquaeous tunneling. 2010 Rock Engineering in Difficult Ground Conditions –Soft Rocks and Karst – Vrklian (ed), Taylor &Francis London.

2.

2. Burger, W. (2013), Multi-Mode TBMs – State of the Art and Recent Developments. 2013 Rapid Excavation & Tunneling Conference & Exhibit, Washington.

3.

3. Duhme, R., Edelmann, T. (2014), Monitoring and Intervention-Free Inspection of TBM Excavation Tools. In Underground Singapore, 2014.

4.

4. Gehrig, M., Kassel, A., Kirenz, K. (2010), Advance Exploration accompanying the Drive: Mixshield with Vision. In Tunnel; 3/2010.

5.

5. Herrenknecht AG, All Around #3 by Herrenknecht – Extreme Tunneling, Schwanau, 2015.

6.

6. Herrenknecht, M., Bäppler, K. (2007), Compressed air work with tunnel boring machines. In Hrdina Bartak (ed.), Underground Space – the 4th Dimension of Metropolises; 2007. London: Taylor & Francis.

7.

7. ITA Working Group No. 5 (2012), Guidelines for Good Working Practice in High Pressure Compressed Air.

8.

8. NFF, Norwegian Tunnelling Society. (2009), Subsea Tunnels. Publication No. 18, Oslo.

9.

9. Schaub, W. 2014. Herrenknecht State of the art TBM technology. BAUMA 2014, Shanghai.

10.

10. Scheffer, M., Rahm, T., Duhme, R., Thewes, M., König, M. (2014), Jobsite Logistic Simulation in mechanized Tunneling. In A. Tolk (ed.), Proceedings of the 2014 Winter Simulation Conference.

(사)한국터널지하공간학회